NEWS
LRA Committee Minutes
Date of next meeting of LRA Committee is: 14th October
If there are items you wish us to consider, comments you wish to make or offers to help please e mail either chair@langstone.org or treasurer@langstone.org
LRA Minutes 2025 Click Here for the current minutes
Flood Committee Reports
Coastal Partners and Langstone meeting March 2025 CLICK HERE
Coastal Partners and Langstone meeting 30.1.25 CLICK HERE
Overview More details in the above attachment - Planning application: submitting end Feb 25. Consultation for 3 months. Construction contract procurement completion expected in June 25 when design will be finalized before planning submission. Project start date April 2026. Project time line available in November. This will take about two years. The design will include a traffic management plan. Highways Authority approached
May 9 Report 2024 Click Here
May 22 Report 2024 Click Here
July 11 Report 2024 Click Here