NEWS

LRA Committee Minutes

Date of next meeting of LRA Committee is: 14th October

If there are items you wish us to consider, comments you wish to make or offers to help please e mail either chair@langstone.org or treasurer@langstone.org

LRA Minutes 2025 Click Here for the current minutes

Flood Committee Reports

Coastal Partners and Langstone meeting March 2025  CLICK HERE

Coastal Partners and Langstone meeting 30.1.25  CLICK HERE

Overview More details in the above attachment - Planning application: submitting end Feb 25. Consultation for 3 months. Construction contract procurement completion expected in June 25 when design will be finalized before planning submission. Project start date April 2026. Project time line available in November. This will take about two years. The design will include a traffic management plan. Highways Authority approached

May 9 Report 2024 Click Here 

May 22 Report 2024 Click Here 

July 11 Report 2024 Click Here 

 